Abstract
The Tohoku Shinkansen Railway between Morioka and Hachinoe was opened on December 1, 2002. In this section, there are 20 tunnels. Second Itsukaichi tunnel is one of them, and it is a relatively short tunnel of 1175 m. At the Morioka portal, this tunnel crosses under National Highway No. 4 with a small depth of overburden 2-5 m where approximately 15,000 vehicles pass a day. The tunnel was excavated by NATM method. All Ground Fasten method was used as an auxiliary method. As a result, the face was prevented from collapsing and the tunnel was excavated while keeping the ground surface settlement to a minimum without interfering with road traffic.