Article ID Journal Published Year Pages File Type
1122087 Procedia - Social and Behavioral Sciences 2012 8 Pages PDF
Abstract

Many Indonesian transportation projects was funded by foreign loans, e.g. projects in Ministry of Transport and Ministry of Public Works. The data used were from Indonesian National Development Planning Agency quarterly report (2006-2010). Descriptive statistics analysis was conducted to the progress variant for each directorate generals. Some t-tests were done to obtain whether in the observation period the mean progress variant for each directorate general was indicating serious delay. Serious delay projects characteristics was mapped. The percentage of serious delay worsened between 2006-2009. Overall serious delay rate was 39%. In general, serious delay occurance started when elapsed time reach 30-40%.

Related Topics
Social Sciences and Humanities Arts and Humanities Arts and Humanities (General)