Article ID Journal Published Year Pages File Type
1134715 Computers & Industrial Engineering 2010 4 Pages PDF
Abstract
This paper considers single machine scheduling problems with setup times and deteriorating jobs. The setup times are proportional to the length of the already processed jobs, that is, the setup times are past-sequence-dependent (p-s-d). It is assumed that the job processing times are defined by functions dependent on their starting times. The following objectives are considered: the makespan, the total completion time, and the sum of earliness, tardiness, and due-window starting time and size penalties. We propose polynomial time algorithms to solve these problems.