Article ID | Journal | Published Year | Pages | File Type |
---|---|---|---|---|
1134715 | Computers & Industrial Engineering | 2010 | 4 Pages |
Abstract
This paper considers single machine scheduling problems with setup times and deteriorating jobs. The setup times are proportional to the length of the already processed jobs, that is, the setup times are past-sequence-dependent (p-s-d). It is assumed that the job processing times are defined by functions dependent on their starting times. The following objectives are considered: the makespan, the total completion time, and the sum of earliness, tardiness, and due-window starting time and size penalties. We propose polynomial time algorithms to solve these problems.
Related Topics
Physical Sciences and Engineering
Engineering
Industrial and Manufacturing Engineering
Authors
Chuanli Zhao, Hengyong Tang,