Article ID | Journal | Published Year | Pages | File Type |
---|---|---|---|---|
1136357 | Mathematical and Computer Modelling | 2011 | 8 Pages |
Abstract
This paper considers a problem of scheduling s-precedence constrained jobs on machines in parallel which have different speeds. The objective is to minimize the weighted total completion time. The s-precedence relation between two jobs ii and jj represents the situation where job jj is constrained from processing until job ii starts processing, which is different from the standard definition of a precedence relation where jj cannot start until ii completes. An LP-based heuristic procedure is derived for the problem. Numerical experiments are conducted to show that the derived heuristic finds effective solutions.
Keywords
Related Topics
Physical Sciences and Engineering
Engineering
Control and Systems Engineering
Authors
Eun-Seok Kim,