Abstract

The single-machine scheduling problems with position and sum-of-processing-time based processing times are considered. The actual processing time of a job is defined by function of its scheduled position and total normal processing time of jobs in front of it in the sequence. We provide optimal solutions in polynomial time for some special cases of the makespan minimization and the total completion time minimization. We also show that an optimal schedule to be a V-shaped schedule in terms of the normal processing times of jobs for the total completion time minimization problem and the makespan minimization problem.