Abstract
This paper presents a new scheduling method for manufacturing system based on the Timed Petri Net model and a reactive fast graph search algorithm. The following two typical problems are addressed in this paper. (1) Minimization of the maximum completion time. (2) Minimization of the total tardiness. As for the problem (1), a new search algorithm which combines the RTA∗ and a rule-based supervisor is proposed. As for problem (2), the original Petri Net model is converted to its reverse model and the algorithm developed for the problem (1) is applied, regarding the due date as the starting time in the reverse model. Some numerical experiments are carried out to demonstrate usefulness of our algorithm.