Article ID Journal Published Year Pages File Type
272520 Fusion Engineering and Design 2011 5 Pages PDF
Abstract

During the operation of the HiPER first engineering facility, up to 1.2 × 105 MJ/yr of fusion neutrons yields are foreseen. This irradiation level could be distributed in 100 MJ detonations, accounting up to 100 detonations in a single burst, with 10 Hz repetition rate. A burst would take place every month. The dose rates are computed and different concrete shields are evaluated within the target bay. During the operation of the facility the entrance is forbidden inside the bioshield. Between bursts, manual maintenance might be performed inside the bioshield but outside the final optics assembly (FOA) shield. Inside the FOA shield the residual dose rates are so high that only remote maintenance is allowed. The FOA shield reduces the delivered dose rate to optics in a factor of 30.3.

Related Topics
Physical Sciences and Engineering Energy Energy Engineering and Power Technology
Authors
, , , ,