Article ID Journal Published Year Pages File Type
286591 Journal of Rock Mechanics and Geotechnical Engineering 2012 11 Pages PDF
Abstract

Rockburst problems induced by high in-situ stresses were prominent during construction of the headrace tunnels of Jinping II hydropower station. The rockbursts occurred in various forms, and it is necessary to take pertinent measures for integrated prevention and control of rockbursts. In view of the rockburst characteristics during tunnel construction of Jinping II hydropower station, the engineering geological conditions were presented, and the features, mechanisms and forms of rockbursts observed during construction were analyzed in detail. A large number of scientific researches, experiments and applications were conducted. Multiple measures were adopted to prevent and control rockbursts, including the prediction and early warning measures, stress relief by blasting in advance, optimized blasting design and optimized tunnel support in the tunnel sections prone to strong rockbursts. The effectiveness of these prevention and control measures was evaluated. Experiences have been accumulated through a great number of helpful explorations and practices for rockburst prevention and control. A comprehensive rockburst prevention and control system has been gradually established.

Related Topics
Physical Sciences and Engineering Earth and Planetary Sciences Geotechnical Engineering and Engineering Geology
Authors
, , ,