Article ID | Journal | Published Year | Pages | File Type |
---|---|---|---|---|
4769349 | Hydrometallurgy | 2017 | 23 Pages |
Abstract
Our investigation covers the first 1000Â days of SSL, with 110 PVC wells distributed across five main areas. During this time, we estimate production at 2.26Â ÃÂ 106Â kg of copper based on the amount of solution introduced through the wells multiplied by the average copper grade from a number of sources, including monitoring wells and newly formed side slope seeps. Some areas performed better than others, especially where assays revealed that acid soluble copper was greater than 50% of total copper. The SSL program is expected to continue for at least another 1000Â days, and we expect an additional 7Â ÃÂ 106 to 15Â ÃÂ 106Â kg will be withdrawn from inventory.