Article ID | Journal | Published Year | Pages | File Type |
---|---|---|---|---|
4922182 | International Journal of Project Management | 2017 | 11 Pages |
Abstract
Through analysis of the Italian system for stakeholder management-the so-called Conferenza di Servizi, which was organised according to stakeholder theory with an emphasis on representation of interested parties-this paper identifies the limitations of representation to predict the fate of a megaproject. Settlements based on interests are not able to capture all relevant actors and all relevant types of knowledge. In contrast to stakeholder theory, Dingpolitics explains project management as a process of finding out the multiple, evolving and sometimes indefinite contours of claims and concerns from many human and non-human actors by analysing both what actors are worried about and how their different concerns, ambitions and claims are composed.
Keywords
Related Topics
Physical Sciences and Engineering
Engineering
Civil and Structural Engineering
Authors
Silvana Revellino, Jan Mouritsen,