Article ID | Journal | Published Year | Pages | File Type |
---|---|---|---|---|
5002678 | IFAC-PapersOnLine | 2016 | 6 Pages |
Abstract
We treat a two-machine job shop scheduling problem with availability constraint on one machine to minimize the makespan. We consider the deterministic case where the unavailability period, corresponding to preventive maintenance tasks, is known in advance and fixed. We assume that jobs are non-preemptive. First, two mixed-integer programming (MIP) models are first presented. Some propositions concerning the optimality of Jackson's algorithm when availability constraint exists is provided. Then a branch and bound (B&B) method is developed to solve the problem. The obtained results prove the efficiency of the proposed B&B.
Keywords
Related Topics
Physical Sciences and Engineering
Engineering
Computational Mechanics
Authors
Mourad Benttaleb, Faicel Hnaien, Farouk Yalaoui,