Abstract
The automation of the temperature elevation test is outlined here for both the oil temperature elevation and the determination of the winding temperature elevation. While automating this test it is necessary to use four thermometers, one three-phase wattmeter, a motorized voltage variator and a Kelvin bridge to measure the resistance. All the equipments must communicate with a microcomputer, which will have the test program implemented. The system to be outlined here was initially implemented in the laboratory and, due to the good results achieved, is already in use in some transformer manufacturing plants.