Abstract

The article presents the problem of balancing work for schedules carried out in accordance with Linear Construction Methods. An example is presented of the construction of concrete surface. A number of schedules were developed for the collected data. The preeminent schedule was chosen and then optimized by curtailing working time of preceding working brigades with aid of subsequent brigades. The article presents a model which assumes that the effectiveness is equal for all brigades. Such an assumption was possible due to the nature of the activities to be performed.