Abstract
Different pathologies may arise on a wall finish if this is applied on a hemp-based rammed wall that is not completely dry. By simulating uneven drying and early-rendering of load-bearing and non-load-bearing hemp concrete blocks (made with natural hydraulic lime only or a mix of lime with clay) and studying them by means of chromatic, microbiological, textural and morphological investigations, we found that: it is advisable to wait at least ten weeks before rendering; adding clay to hemp concrete delays drying, leading to more intense deterioration of the render; natural hydraulic lime is the preferred binder for rendering hemp concrete.
Keywords
Related Topics
Physical Sciences and Engineering
Engineering
Civil and Structural Engineering
Authors
A. Arizzi, M. Brümmer, I. MartÃn-Sánchez, E. Molina, G. Cultrone,