Article ID | Journal | Published Year | Pages | File Type |
---|---|---|---|---|
6972982 | Journal of Loss Prevention in the Process Industries | 2017 | 30 Pages |
Abstract
Strategies such as providing a SIF on the common outlet from a wellhead tower, providing additional relief capacity and reducing sources of common cause failures were found to be effective in increasing the risk reduction factor achieved by the over-pressure protection system. Where such measures are insufficient, an alternative solution is to design all lines to the well shut-in pressure. This approach transfers the risk of over-pressure to the downstream separator, which must then be provided with adequate protection measures.
Related Topics
Physical Sciences and Engineering
Chemical Engineering
Chemical Health and Safety
Authors
Arjan Abeynaike, Venkatesh Sourirajan,