Article ID Journal Published Year Pages File Type
7168551 Engineering Failure Analysis 2013 10 Pages PDF
Abstract
This article concerns the loss of a Horizontal Directional Drilling crossing due to a failure that took place during pullback of the pipeline. The more than 500 m long drilling was meant to lodge a 30″ pipeline that crossed a large river. The failure caused the total loss of the crossing, and the necessity to repeat the entire process in another, less favorable location. Root causes involved a difficult soil composition, and constraints at a populated bank that led to engineering solutions not proved before on a pipe of such diameter. Discontinuities on the tunnel and the use of a sacrifice pipe at the front end of the pipe column, which was related to the need for more pipes than originally calculated because of a series of problems at the beginning of the perforation, were also defined as root causes. Lessons learned are highlighted.
Related Topics
Physical Sciences and Engineering Engineering Industrial and Manufacturing Engineering
Authors
, , ,