Abstract
The other issue arises, while planning and scheduling compressed projects with DSM. When the activities are overlapped to achieve the compressed duration, there arise two cases - the natural overlap (involving minimum risk) and the forced overlap (involves more risk). This paper focuses on the estimation of natural overlap project duration using DSM. Further, the author also proposes a detailed implementation procedure focusing on the above ideas and is illustrated through an example.