Abstract

•The paper presents an automatic 4D CAD updating methodology using image processing.•The methodology includes image-based progress monitoring and 4D model development.•The method succeeds in automating almost the entire process of 4D updating.

For a four-dimensional (4D) computer-aided design (CAD) model to be useful for users throughout a construction project, the model must be updated in a timely and accurate manner during the construction. Only when it has been properly updated can the 4D CAD model reflect the real progress of a construction site to inform managerial decision making. However, updating a 4D CAD model is time-consuming and labor-intensive because the full updating process, from site data acquisition to 4D model regeneration, is typically conducted manually. This difficulty in updating a 4D model discourages industry practitioners from actively adopting 4D models. This paper presents an image processing-based methodology for the automatic updating of a 4D CAD model. Characterized by 3D CAD-based image mask filters, color-based noise removal, and area-based progress calculation, the image processing approach provides as-built schedule information. The schedule information is then automatically integrated with an existing 3D CAD model in batch-processing modes to produce the updated 4D CAD model. The proposed methodology was applied and verified in a cable-stayed bridge construction project and is expected to facilitate the wider use of 4D CAD models in the construction industry.

Related Topics
Physical Sciences and Engineering Engineering Civil and Structural Engineering
Authors
, , ,