Abstract

•Gives a comprehensive survey about the most important critiques of PERT•Gives a comprehensive survey about the most important developments of PERT•Shows the effects of activity calendars on distribution of the project duration•Opens new gateways to the research of PERT

The Program Evaluation and Review Technique (PERT) has been criticized for the proposed (beta) distribution of the activities, the three-point estimation method, the assumption of task independence and the assumed distribution of the project duration since its birth. Developments and generalizations of the succeeding years and decades were mostly aimed at resolving these issues. However, there are still pending questions that have not been examined in detail, if at all. One of these issues is the effect of activity calendars on the distribution of the project duration. Using a simple artificially created project we prove that the application of activity calendars has a greater influence on the distribution of the project duration than any of the above-mentioned criticisms. In the absence of analytic solutions, a robust tool performing Monte Carlo simulations has been used for calculations.

Related Topics
Physical Sciences and Engineering Engineering Civil and Structural Engineering
Authors
,