Article ID Journal Published Year Pages File Type
480876 European Journal of Operational Research 2010 4 Pages PDF
Abstract

A set of independent, resumable and proportionally deteriorating jobs is to be executed on a single machine. The machine is not continuously available for processing but the number of non-availability periods, the start time and end time of each period are known in advance. The criterion of schedule optimality is the maximum completion time. It is proved that the decision version of the problem with a single non-availability period is ordinarily NPNP-complete. It is also proved that for the problem with a single non-availability period there exists a fully polynomial-time approximation scheme. Finally, it is proved that for the problem with two or more non-availability periods there does not exist a polynomial-time approximation algorithm with a constant worst-case ratio, unless P=NPP=NP.

Related Topics
Physical Sciences and Engineering Computer Science Computer Science (General)
Authors
, ,