Article ID Journal Published Year Pages File Type
481615 European Journal of Operational Research 2011 10 Pages PDF
Abstract

In this paper, we propose a heuristic method for resource constrained project scheduling problem with fuzzy activity times. This method is based on priority rule for parallel schedule generation scheme. Calculation of critical path in this case requires comparison of fuzzy numbers. Distance based ranking of fuzzy number is used for finding the critical path length and concept of shifting criticality is proposed for some of the special cases. We also propose a measure for finding the non-integer power of a fuzzy number. We discuss some properties of the proposed method. We use an example to illustrate the method.

Related Topics
Physical Sciences and Engineering Computer Science Computer Science (General)
Authors
, , ,