In this paper, a new buffer monitoring approach is introduced, which sets tolerance limits for Earned Value Management/Earned Schedule (EVM/ES) schedule performance metrics by allocating the project buffer over the different project phases. The purpose of these tolerance limits is to provide the project manager with accurate and reliable information on the expected project outcome during the project execution. A computational study is carried out to assess the performance of the proposed approach and to compare its performance with traditional buffer consumption monitoring procedures. Additionally, existing performance metrics for tolerance limits have been put into a hypothesis testing framework, and new metrics have been developed in order to fill the detected gaps in performance measurement. Results have shown that the proposed tolerance limits improve the performance of the monitoring phase, especially for parallel projects. Consequently, the underperformance of EVM/ES for parallel projects is mitigated by these limits.
Related Topics
Physical Sciences and Engineering Computer Science Computer Science (General)
Authors
, ,