Article ID Journal Published Year Pages File Type
6752010 Journal of Rail Transport Planning & Management 2017 14 Pages PDF
Abstract
This paper considers multi-stage train formation with mixed usage tracks at a marshalling yard without departure yard. A novel integer programming model for scheduling shunting tasks as well as allocating arrival yard tracks and classification bowl tracks is presented. By taking a comprehensive view of the marshalling yard operations, more effective schedules can be found, and a variety of characteristics can be optimised, including shunting work effort, number or cost of tracks, and shunting task start times. Two different objective functions are evaluated: minimising work effort in terms of wagon pull-backs and minimising track costs. A procedure for finding a hot-start solution with few wagon pull-backs is also presented. The proposed model is tested on real data from Sävenäs marshalling yard in Sweden. The results show that the method is able to return an optimal schedule for a planning period of 4 days if the hot-start solution is optimal or the remaining problem is tractable for the heuristics in CPLEX.
Related Topics
Physical Sciences and Engineering Computer Science Computer Science Applications
Authors
, , , ,