Abstract
► 1.78 million km2 of Western Australia is identified as technically suitable. ► Hypothetical production potential of technically suitable area ≈908,000 TW h/year. ► Only 0.6% of technically suitable areas considered to be medium-very highly suitable. ► Site suitability highly dependent on availability of infrastructure and load. ► Suitable areas still more than sufficient to motivate CSP production.