Abstract
This paper investigates two-machine flow shop scheduling problems taking transportation into account. The finished jobs are transferred from the processing facility and delivered to customers by truck. Both transportation capacity and transportation times are explicitly taken into account in these models. We study the class of flow shop problems by analysing their complexity. For the makespan objective function, we prove that this problem is strongly NP-hard when the capacity of a truck is limited to two or three parts with an unlimited buffer at the output of the each machine. This problem with additional constraints, such as blocking, is also proven to be strongly NP-hard.