Four-day service-staff work-week in order to complete maintenance operations more effectively in a Nigerian power-generating station
موضوعات مرتبط
مهندسی و علوم پایه مهندسی انرژی مهندسی انرژی و فناوری های برق
پیش نمایش صفحه اول مقاله
Four-day service-staff work-week in order to complete maintenance operations more effectively in a Nigerian power-generating station
چکیده انگلیسی

Labour costs represent the major portion of the total cost in many industries and activities. This investigation examines a four-day workweek (compared with the current five-day week schedule) for maintenance operations in the Power Holding Company of Nigeria (PHCN). The aim is to reduce maintenance labour-costs, while satisfying increasing demands for higher effectiveness. Changing from the five to a four-day workweek for maintenance personnel at the Afam power-station is predicted to produce savings of 10% of maintenance labour cost without any loss of output or quality of service.

ناشر
Database: Elsevier - ScienceDirect (ساینس دایرکت)
Journal: Applied Energy - Volume 84, Issue 10, October 2007, Pages 1044–1055
نویسندگان
, , , ,