Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times
موضوعات مرتبط
مهندسی و علوم پایه مهندسی کامپیوتر علوم کامپیوتر (عمومی)
پیش نمایش صفحه اول مقاله
Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times
چکیده انگلیسی

In this paper, a multi-mode resource-constrained project scheduling problem with schedule-dependent setup times is considered. A schedule-dependent setup time is defined as a setup time dependent on the assignment of resources to activities over time, when resources are, e.g., placed in different locations. In such a case, the time necessary to prepare the required resource for processing an activity depends not only on the sequence of activities but, more generally, on the locations in which successive activities are executed. Activities are non-preemptable, resources are renewable, and the objective is to minimize the project duration. A local search metaheuristic—tabu search is proposed to solve this strongly NP-hard problem, and it is compared with the multi-start iterative improvement method as well as with random sampling. A computational experiment is described, performed on a set of instances based on standard test problems constructed by the ProGen project generator. The algorithms are computationally compared, the results are analyzed and discussed, and some conclusions are given.

ناشر
Database: Elsevier - ScienceDirect (ساینس دایرکت)
Journal: European Journal of Operational Research - Volume 187, Issue 3, 16 June 2008, Pages 1238–1250