Delay causes in Iran gas pipeline projects
موضوعات مرتبط
مهندسی و علوم پایه سایر رشته های مهندسی مهندسی عمران و سازه
پیش نمایش صفحه اول مقاله
Delay causes in Iran gas pipeline projects
چکیده انگلیسی

On the basis of Iran's strategic development plan, natural gas industry must develop the capacity of gas transmission up to 1300 million m3 per day until 2025. For this purpose, gas pipeline length should be doubled during the next 15 years; however, experience shows a remarkable delay in nearly all gas pipeline projects. The main goal of this paper is to identify and rank the causes of delay in these kinds of projects in Iran. In this regard, 24 executed gas pipeline projects were studied and then extracted delay factors were conferred with 10 experts from several disciplines. The result was a 43-item list of factors which then was ranked by means of a questionnaire survey. The result reveals that the 10 major delay factors are: “imported materials, unrealistic project duration, client-related materials, land expropriation, change orders, contractor selection methods, payment to contractor, obtaining permits, suppliers, and contractor's cash flow”.


► In literature review, causes of delay were investigated in 22 projects in 3 fields.
► A comparative list of the delay factors in 18 projects revealed common factors.
► 43 common delay causes in Iran gas pipeline projects were identified.
► Ranking of the delay causes was performed through a questionnaire survey.
► Material-related causes and unrealistic project duration are the top factors.