کد مقاله کد نشریه سال انتشار مقاله انگلیسی نسخه تمام متن
5080726 1477579 2013 13 صفحه PDF دانلود رایگان
عنوان انگلیسی مقاله ISI
Constraint-based ACO for a shared resource constrained scheduling problem
موضوعات مرتبط
مهندسی و علوم پایه سایر رشته های مهندسی مهندسی صنعتی و تولید
پیش نمایش صفحه اول مقاله
Constraint-based ACO for a shared resource constrained scheduling problem
چکیده انگلیسی
We consider a scheduling problem arising in the mining industry. Ore from several mining sites must be transferred to ports to be loaded on ships in a timely manner. In doing so, several constraints must be met which involve transporting the ore and deadlines. These deadlines are two-fold: there is a preferred deadline by which the ships should be loaded and there is a final deadline by which time the ships must be loaded. Corresponding to the two types of deadlines, each task is associated with a soft and hard due time. The objective is to minimize the cumulative tardiness, measured using the soft due times, across all tasks. This problem can be formulated as a resource constrained job scheduling problem where several tasks must be scheduled on multiple machines satisfying precedence and resource constraints and an objective to minimize total weighted tardiness. For this problem we present hybrids of ant colony optimization, Beam search and constraint programming. These algorithms have previously shown to be effective on similar tightly-constrained combinatorial optimization problems. We show that the hybrid involving all three algorithms provides the best solutions, particularly with respect to feasibility. We also investigate alternative estimates for guiding the Beam search component of our algorithms and show that stochastic sampling is the most effective.
ناشر
Database: Elsevier - ScienceDirect (ساینس دایرکت)
Journal: International Journal of Production Economics - Volume 141, Issue 1, January 2013, Pages 230-242
نویسندگان
, , , ,