Efficient multi-product multi-BOM batch scheduling for a petrochemical blending plant with a shared pipeline network
ترجمه فارسی عنوان
برنامه ریزی چند بمب چند محصول چند کاره برای کارخانه ترکیبی پتروشیمی با یک شبکه خط لوله مشترک
کلمات کلیدی
برنامه ریزی دسته ای، ترکیب شیمیایی گیاه، ابتکاری
موضوعات مرتبط
مهندسی و علوم پایه مهندسی شیمی مهندسی شیمی (عمومی)
چکیده انگلیسی


• Effective scheduling heuristic for multi-product production planning of a real size petrochemical blending plant by dynamic prioritization-based greedy search.
• Incorporation of shared pipelines, product recipes, product families, capacity constraints, dwell times and dedication constraints.
• Scheduling of short to mid-term operations and tactical evaluation of plant configurations or production policies.

We present an effective scheduling heuristic for realistic production planning in a petrochemical blending plant. The considered model takes into account orders spanning a multi-product portfolio with multiple bills of materials per product, that need to be scheduled on shared production facilities including a complex pipeline network. Capacity constraints, intermediate storage restrictions, due dates, and the dedication of resources to specific product families have to be respected. The primary objective of the heuristic is to minimize the total order tardiness. Secondary objectives include the minimization of pipeline cleaning operations, the minimization of lead times, and the balanced utilization of filling units.The developed algorithm is based on a dynamic prioritization-based greedy search that schedules the orders sequentially. The proposed method can schedule short to mid-term operations and evaluate different plant configurations or production policies on a tactical level. We demonstrate its performance on various real-world inspired scenarios for different scheduling strategies.Our heuristic was used during the construction phase of a new blending plant and was instrumental in the optimal design of the plant.

ناشر
Database: Elsevier - ScienceDirect (ساینس دایرکت)
Journal: Computers & Chemical Engineering - Volume 84, 4 January 2016, Pages 493–506